Construction is progressing at Centennial Secondary School. The school is scheduled to be completed for opening in September.
Some of what is currently happening on site includes:
- Gypsum Board installation and mudding nearing completion
- Flooring is underway
- Millwork installation is underway
- Ceiling grids and lighting are in
- Teaching Kitchen installation is almost complete
- Exterior cladding and insulation is underway
- Rough grading is complete
- Top soil provision has started
- Building is totally enclosed
- Roofing is nearing completion
- Theatre is at rough in stage for services and almost ready for boarding.